How to create WBS
Initiation->Planning->Execution->Closed->Financials
Project Name->Phases->Deliverables(draft->review->approval)
Milestone is with 0 days duration
FS, SS, FF, SF to use comparing precessor vs. successor
Auto scheduling always
How to track
- Change working time -> new calendar to apply holidays, and do not forget to change project calenda
- Baseline per alignment with PMO or technical team
- Baseline only to ver 10 days late or 20 days early
- 0%, 25%, 50%, 100% to right time on right deliverables
How to manage changes
- Change only happen during execution stage but not planning phase
- Can be processed for a Closed project
- Scope change on project to update estimate in PPM as well
- CAP vs. EXP vs. Support costs are always expensed - never capitalized
- Budget locked in Dec, 1st Projection in April, 2nd One in August
How to define PM scope
- Time, quality, cost
- Finacials including non-IT, IT consumption, IT Infrastructure
- Labor vs. service vs. software vs. expense
How to report project
- RAID - risk, action, issue, decision
- An uncertain event or condition that, if it occurs, has a positive or negative effect on a project's objectives
- An event or condition that has or will happen that has a postive or negative effect on a project's objectives
- Team status report - designed for project and workstream team meetings
- Executive status report - pypically one page to contains high level project status